Project Files‎ > ‎

DGP 11-02 - Ruston Sewer Project

Applicant Contact Info:
Town of Ruston
5117 North Winnifred Street
(253) 759-3544
 
Agent Contact Info:
Jerry Morrissette
Town Engineer
(360) 352-9456
 
Project Description:
The scope of work consists of the installation by open trench methods of approximately 14,000 LF of 8-inch sanitary sewer main, 260 sanitary sewer laterals including 4,000 LF of 6-inch diameter pipe, and 76 sanitary sewer manholes.  Location of work will be on Pearl Street, Highland Street, Winnifred Street, Shirley Street, 49th Street, Rust Way, 50th Street, Commercial Street, 52nd Street, and various alleys as shown on the construction plans.

Estimated quantity of imported fill material is 20,000 tons.  Estimated quantity of exported material is 12,000 cubic yards.  The allowed time for construction is 270 working days.
 
Project Location:
Located throughout Ruston, (please see the attached documentation for additional location information).
 
 
Permit Review Status:
Showing 7 items
DepartmentStaffStatus
Sort 
 
Sort 
 
Sort 
 
DepartmentStaffStatus
Building Mike Barth Completed/Comments Received 
Engineering Jerry Morrissette Completed/Comments Received 
Fire Don Torbet Completed/Comments Received 
Operations Steve Taylor N/A 
Planning Rob White Completed/Comments Received 
Police Jeremy Kunkel N/A 
SEPA - exempt Rob White Completed/Comments Received 
Showing 7 items
Ċ
Rob White,
Jun 8, 2011, 8:08 AM
Ċ
Rob White,
Jun 8, 2011, 8:09 AM
Ċ
Rob White,
Jun 8, 2011, 8:13 AM
Ċ
Rob White,
Jun 8, 2011, 8:16 AM
Ċ
Rob White,
Jun 8, 2011, 8:36 AM
Ċ
Rob White,
Jun 8, 2011, 8:10 AM