Ruston Alley Repaving Schedule

posted Jun 14, 2013, 2:53 PM by Town Clerk

Rodarte will complete repaving in three alleys located at 51st and 52nd between Shirley and Winnifred Streets, 52nd and 53rd between Shirley and Winnifred Streets, 52nd and 53rd between Highland and Winnifred Streets.  A notice will be distributed to each home affected prior to commencing work:


Below is the schedule for repaving of the alleys:

Monday - June 17th               Removal of existing asphalt

Tuesday - June 18th              Removal of existing asphalt / minor regarding activities

Wednesday - June 19th       No construction activities

Thursday - June 20th         No construction activities

Friday - June 21st             Repaving of alleys


Please contact Ruston City Hall for any questions at 253-759-3544.