Update: EPA Phasing Plan and Schedule Status Maps

Posted on June 3, 2019


The following information details the completed and upcoming EPA Phasing construction plans for the Point Ruston Development. Click this link to view the EPA schedule status maps.

Phase 1 Construction:

  • Building 2 – Completed
  • Sediment cap – Completed
  • Water walk – Completed
  • Slag Peninsula cap – Completed

Phase 2 Construction:

  • Buildings 1 – Completed
  • Building 18 – Completed
  • Building 8 – Completed
  • Building 17 – December 31, 2019
  • Buildings 9 – June 30, 2020
  • Building 11 – June 30, 2020

Phase 3 Construction:

  • Building 6 – Completed
  • Building 3 – Completed September 2018
  • Building 5 – Completed September 2018
  • Building 7 – August 31, 2019
  • Building 4 – June 30, 2020

Phase 4 Construction:

  • Building 12 –June 30, 2019
  • Building 14 – June 30, 2019
  • Building 10C (former cooling pond) – June 30, 2020
  • Car tunnel (Lot 10) – June 30, 2019
  • Buildings 15B&C – June 30, 2020
  • Building 16 – June 30, 2021
  • Building 15A – June 30, 2021
  • Yacht Basin sediment – December 31, 2024